Detailed Design Submissions

merrifield overhead 2023.jpg

This page is to assist developers and their agents with the Engineering and Landscape requirements for large scale developments and to clarify the process for submitting detailed design forms to Council. 

If you are seeking information about subdividing an existing residential property, please see Subdividing residential property

Landscape Designs

Step 1.Get your documents ready

Before submitting your detailed landscape designs form to Council, you should have the following documents ready to be uploaded:

  • An Opinion of Probable Cost (OPC) - Excel File
  • Concept Plans
  • Arborist Report
  • CHMP
  • DECCA Conservation Management Plan
  • Landscape Values Management Plan
  • Landscape Plans
  • Technical Specifications

Step 2.Submit your submission

Once you have all of the above documents, you are ready to submit your submission form to Council. This can be done online or using our or printable form.

Landscape Detailed Design Form 

Step 3.Our Internal Process

Approval of Detailed Design Plans can take 30 working days from submission to finalise. This timeline allows for 8 days of administrative processing. If council requires further information from you, we will advise you of the statutory clock stopping. 

An officer will be assigned to your submission, and you will be provided with a landscape fees invoice. Once paid, the Detailed Design review process will begin, and we will assess your submission. 

For more information about our internal process, please see the process tab above.

Step 4.Submission outcome

If your submission is approved, approved plans will be forwarded to your nominated email address.

Civil Designs

Step 1.Get your supporting documents ready

Before submitting your civil detailed design form to Council, you will need to have all required documents ready to be uploaded. This includes your design drawings, landscape plans, traffic assessment report and many other important documents. 

See required documents list below

Step 2.Submit your submission

Once you have the required documents ready, you are ready to submit your design submission to Council. This can be done online or by using our printable form. Applicants must use either of these forms when submitting their design to Council. 

Civil Detailed Design Form 

Step 3.Our Process

Approval of Detailed Design Plans can take 30 working days from submission to finalise. This timeline allows for 8 days administration time. If Council requires further information from you when making a decision, the statutory clock will stop.  Please note the stop and start of the clock will be communicated to the applicant. Please see the process tab above for more information about how we handle these submissions. 

Step 4.Submission outcome

Once your submission has been fully assessed by an officer, you will be advised of an application outcome. Approval of Detailed Design Plans can take 30  days to finalise excluding additional administration process times. 

If your submission is approved, approved plans will be forwarded to your nominated email address.

Our Process

Step 1.Submission

Complete your civil or landscape detailed design form via openforms and submit it for review

Step 2.Initial Review

Your submission will be entered into our tracking software and assigned to an engineer. The engineer assigned to your submission will check it for completeness and inform you if any required documents are missing.

Step 3.Invoice

Once all required information is confirmed as having been received, an invoice will be raised and sent to you via email.

Step 4.Detailed Design Review Begins

Once your invoice has been confirmed as paid, a statutory clock will begin, and the detailed review of your submission will commence. 

Step 5.Request for Further Information 

In assessing your submission, our engineer will compile a request for further information. This will generally take 10 to 15 working days from the date your invoice was paid. Your RFI will clearly set out the information required from you and the process for submitting it. Once your RFI has been issued to you, the statutory time clock will be paused while Council awaits your response.

If your response to the request for further information is incomplete, Council will notify you of the items required before the submission can be accepted. 

Step 6.Plan Approval

Once you have addressed all outstanding requirements in the request for further information, Council will complete your review and provide you with an approval letter and stamped plans. This process can take an additional three working days following the review of your submission being completed by our engineer. 

Required Documents for Civil Detailed Design

You will need to provide electronic copies of the below documents when submitting your civil detailed design application form to Council:
  • Approved Functional Layout Plan
  • Design Drawings in an approved format such as PDF
  • Landscape Plans
  • Public Lighting Plans
  • Drainage Concept
  • Drainage Catchment Plan
  • Melbourne Water Drainage Scheme Plans
  • Tree Removal/Retention Plans
  • Traffic Assessment Report
  • Geotechnical Report
  • Road Safety Design Audit Report
  • Pavement Design
  • Water Main Reticulation Plans
  • Sewer Main Reticulation Plans
  • Recycled Water Reticulation Plans
  • Environmental Control Documents
  • Approved Permit Plan
  • TMP & CEMP
  • Estimate of Costs Schedule
  • Drainage Computations for Q5 and Q100